Construction progress
Current readiness55%
01.06.2026 · 55%
Facade and engineering systems
Facade insulation 60% complete. Heating, water supply and electrical systems installed. Window installation started.
15.04.2026 · 42%
Masonry and monolithic works
Walls of two new superstructure levels built. Roof structure of main volume installed. Engineering systems routing started.
20.02.2026 · 28%
Reinforcement of load-bearing structures
Foundation and column reinforcement of existing building complete. New floor slabs in extension started. Temporary supports installed.
12.12.2025 · 15%
Demolition and preparation
Internal partition demolition in existing building complete. Load-bearing structure survey conducted. Foundation reinforcement works started.
05.10.2025 · 8%
Design and permit documentation received
All construction and renovation permits obtained. General contractor agreement signed. Site preparation started.